So, what happened to the Tz5oo Billion World Bank loan to transform the flood-prone?

Nobunaga

JF-Expert Member
Joined
Mar 22, 2019
Posts
1,205
Reaction score
5,121
In October 2022, the World Bank announced the approval of new financing worth $200 million (more than TZS 500 billion) for the Msimbazi Basin Development Project in Tanzania's commercial hub Dar es Salaam.

According to the World Bank, the loan was expected to help reduce the flood exposure of over 300,000 people, including many low-income communities, while providing access to better infrastructure and services.

The bank said the project "will also help ๐’•๐’“๐’‚๐’๐’”๐’‡๐’๐’“๐’Ž ๐’‚ ๐’‡๐’๐’๐’๐’…-๐’‘๐’“๐’๐’๐’† ๐’‚๐’“๐’†๐’‚ ๐’Š๐’ ๐’•๐’‰๐’† ๐’„๐’†๐’๐’•๐’“๐’† ๐’๐’‡ ๐’•๐’‰๐’† ๐’„๐’Š๐’•๐’š ๐’Š๐’๐’•๐’ ๐’‚ ๐’—๐’Š๐’ƒ๐’“๐’‚๐’๐’• ๐’ˆ๐’“๐’†๐’†๐’ ๐’”๐’‘๐’‚๐’„๐’† ๐’‚๐’๐’… ๐’„๐’๐’Ž๐’Ž๐’†๐’“๐’„๐’Š๐’‚๐’ ๐’‚๐’๐’… ๐’“๐’†๐’”๐’Š๐’…๐’†๐’๐’•๐’Š๐’‚๐’ ๐’‚๐’“๐’†๐’‚ that will benefit all residents of Dar es Salaam".

โญ๏ธ Fast forward to 12 November 2023, this video taken today highlights a familiar problem for residents of the Msimbazi valley -- another rain reason, another flood.

It seems that little, if any, has changed to improve the infrastructure of the area, despite the government taking a loan worth more than half a trillion shillings from the World Bank to fix the problem.

What happened to the money?

Your browser is not able to display this video.


Credit: Tanzania Business Insight, X Page.

Rejea: Tanzania yapewa mkopo nafuu wa trilion 1.24 kutekeleza mradi wa REA na daraja la Jangwani mto Msimbazi
 
Andika kiswahili ili hata sisi tunaojua KKK (Kusoma, kuhesabu na kuandika kiswahili) tuelewale dhumuni la bandiko lako.
 
Kama unajipenda kuna maeneo ni ngumu kukaa wala kulazimisha kukaa unajijua upo sehemu gani miaka nenda rudi huchukui hatua acha wazitafune maana wanajua wanaopata taabu hawana pakusemea
 
You secure a loan in October, 2022 and expect to finish a half a trillion shs project in a year?
From securing the loan to implementing the project and finishing it should take at least three to five years if not more.
They haven't even finished the acquisition and compensation of the hard-headed residents yet.
 
Tutendeeni haki wana JF wa Mbauda, Nyarugusu, Bukombe na Itigi.
 
Mkuu ebu fafanua kiufasaha hueleweke.
 
Approval ni sawa na disbursement?
 
Mkuu ebu fafanua kiufasaha hueleweke.
Loan ikishakuwa approved, inarekodiwa na Benki kuu kama approved. inaweza kuchukua zaidi ya mwaka kuwa disbursed na ikishakuwa disbursed inarekodiwa na benki kuu kama disbursed.

Halafu ndio muanze sasa ku-implement project ambayo inahusisha land acquisition, muanze kuzozana na NGos na wanasheria kwa sababu kila mtu atataka kula. Watu wagome kuondoka, mpaka muwaondoe na kusafisha eneo na kuanza project, miaka kadhaa itapita.

Halafu ndio mmalize, mmualike raisi na ngoma, na muwalipe walimu waje kushika vibendera na washone sare hiyo itakuwa around 2028 - 2030.
 