Construction of the multi-million rail project is expected to begin in 2018 and will link Northern Uganda to South Sudan and Rwanda
Uganda has prioritized the 273Kms Malaba β Kampala route, which is expected to cost $2.3 billion.
Project authorities say there in advanced stages of a financial closure with Chinaβs EXIM Bank.
Land compensation and acquisition negotiations had delayed the project for years but it seems it has finally been sorted out.
Available reports indicate that over 60 per cent of the project land has been acquired and compensation of the affected persons is on-going.
Uganda insistence on a guarantee from the Kenyan government, that the section of the railway will reach the Kenya β Uganda border town of Malaba had also dragged the project from commencing on time.
Uganda Project authorities say if all goes as planned, construction is expected to begin in 2018.
The project is expected to extend to Northern Uganda through to South Sudan and later to Rwanda through Western Uganda.
Once completed the SGR is expected to reduce heavy traffic along Malaba - Kampala route, easing road wear in the process not to mention interlinking the East African economies.