Update:
The contractor for the 47km Masindi-Biiso road, China Railway Seventh Group Company Limited (CRSG), must complete the long-delayed project by February 2027, Works and Transport minister Fred Byamukama has directed.
Byamukama issued the directive on Thursday while inspecting the road, which is among critical oil roads being constructed in the Bunyoro sub-region.
The broader road project covers 106km, comprising the Masindi-Biiso (47km), Kabaale-Kiziranfumbi and Hohwa-Nyairongo-Kyarushesha-Butoole roads, at a combined cost of Shs 504 billion.