Akii-Bua stadium ahead of timeline, Uganda Government Insists

Akii-Bua stadium ahead of timeline, Uganda Government Insists

Eronda

JF-Expert Member
Joined
Dec 16, 2025
Posts
1,157
Reaction score
590
Akii-Bua stadium is on track for early completion as the construction of the stadium has reached 40 percent complete and on track for December 2026 finish, Seven months ahead of the original February 2027 target boosting Uganda’s preparations for the AFCON 2027 at a cost of shs. 470billion.

The construction of the Multi sport stadium was launched on May 3, 2025 and was initially expected to be completed in February 2027

SAMCO National Construction Company has however indicated that works are progressing faster than planned, with completion now projected for December 2026, within an 18 month timeline.

“Construction has advanced steadily particularly on the roof structure and about 25 Percent of the work has been completed” Mohammed Nazih, Project manager said.

The state minister for sports Peter Ogwang pointed out that the progress of the project reflects strong coordination between government and the contractors.

He also pointed out that Ali-Bua stadium is a long term national asset designed to host international competitions for decades

Mr. Peter Ogwang further warned gaps in supporting infrastructure particularly in the hospitality sector where he urged private investors in Lira City to develop high end accommodation.

Once completed, the project will include a 20,000 seater main stadium with an athletics track and at-least two changing rooms. It will also include a 2000 seater indoor multi sports arena, Swimming pool and outdoor courts for basketball, Volleyball, netball and badminton.

IMG_4837.jpeg

Current status


IMG_4835.png

Proposed plan
 