Duh, umeamua kutolea watu jicho... Shida ni kwamba unaongea na mazombie, yatapita sikio moja na yatoke na sikio jengineFACT
Tanzania:
sgr phase 1 (200 km) is incomplete three years later and late by a whole year(Has been at 60%-70% since last year june). No trains have been procured. The companies supplying materials to the contractor are going bankrupt.
GOT is now going to look for sgr financing(Commercial loan) from standard chartered bank and a consortium of other banks, excuse given for this massive delay is heavy rains from last year .The population actually bought this line of reasoning (In Kenya this baloney would be called out by the public).
Kenya:
Phase 1 (485 km) took three years to complete(on time) with Nairobi ICD expanded and upgraded. Phase 2A (125 km) completed on time and fully functional with Naivasha ICD constructed from scratch.14,000 trains in 1000 days since launch in 2017 with no delay, no accidents.
Carlsberg putting up a Kes 6 Billion factory in Naivasha special economic zone to take advantage of sgr and icd to export to the african market.50 other multinationals have booked space at naivasha special economic zone.
Mombasa special economic zone construction on track phase 1 to be completed in 2022 with Toyota as anchor tenant. 72 Japanese companies have expressed desire to put up shop in the special economic zone.
Planned Kisumu special economic zone will take raw materials from neighboring countries and add value to them then export to Africa.
Conclusion: Kenya is more strategic not just by building the sgr on time and on budget but also by putting up supporting industries in the special economic zones that will take advantage of the sgr. Carlsberg will export it's flagship brand from Naivasha to the rest of africa using the sgr to get to Mombasa and to get imports easily.
Toyota will use the sgr to transport vehicles from dongo kundu special economic zone to the hinterland for export to Uganda, Rwanda, Burundi and mombasa port for export to the rest of africa.
Kenya is targeting to use the sgr to revamp and turbo charge manufacturing activity with the sgr at the centre of all operations not just to transport imports and transit goods to neighbors.
Very good answer, you can't compare time to complete construction of a technological inferior rail like the one the Chinese built for Kenya with the more technological advanced one been build in Tanzania.
... "Apples vs. Tomatoes" ... no no no way🙂
Hizi ni visingizio vya wajinga, hata kama Kenya ingekua haijajenga reli, hili swala bado lingekua relevant... Sio wakenya ndo waliamka siku moja na wakaamua reli ya 200km ya Tanzania inafaa kujengwa kwa miaka miwili...... Mwenye aliepewa kandarasi ndo alisema hivyo! Alisema ataijenga reli kwa muda flani na baada ya huo muda reli itakua imekamilika inafanya kazi, muda ulipofika karibu akasongeza miezi, miezi iivyosonga akapeleka completion date mbele zaidi hadi nadhani amepitisha mwaka mzima sasa..... Kisa eti mvua, kwani kwa feasibility study hawakupima mvua ya Tanzania na ku incoporate hio mvua kwa timeline ya ujenzi?Do not compare the time of completion btn ur diesel sgr and Tz electric sgr, u have never built electric railways, just compare ur sgr to our mgr because they are the same.
Punguza Ujinga, Arema standard ya Tanzania ni sawa na Chinese class 2 ya ethiopia. Angalia ethiopia, ujue kule reli yenu ambayo bado ni ndoto itakapoelekea.Do not compare the time of completion btn ur diesel sgr and Tz electric sgr, u have never built electric railways, just compare ur sgr to our mgr because they are the same.
Nikiongelea kuhusu watu ambao hua wanaongea kishabiki hua naongelea mambo kama haya, huu hapa sasa ndo mfano mzuri kabisa, Ukifwata maono ya watu kama hawa ndo utajikuta unachukia vitu vingi kumbe kisa unakula propaganda za kiushabiki...Wakenya[emoji23][emoji23][emoji23]
View attachment 1478225
View attachment 1478226
View attachment 1478227
View attachment 1478228
View attachment 1478229
Nikiongelea kuhusu watu ambao hua wanaongea kishabiki hua naongelea mambo kama haya, huu hapa sasa ndo mfano mzuri kabisa, Ukifwata maono ya watu kama hawa ndo utajikuta unachukia vitu vingi kumbe kisa unakula propaganda za kiushabiki...
Reli ya Senegal ni only 55km, tena ni reli ya Abiria pekee, haibebi mizigo..... Reli yenyewe imejengwa kwa garama ya $500m
Thus, the express service will become the Senegalese first airport rail link. The total project costs 400 million Euros.
The express trains will cover the entire line in 2020 with a maximum speed of 160 kilometres per hour. They will stop at 14 stations and will ride the 55-kilometre route in 45 minutes. The estimated daily ridership is 115,000 passengers.
Senegal launches first express train
$500 Million / 55km = $9 Million per KM kwa reli ya kubeba abiria pekee. Tena ukifwatilia vizuri sio 55km zote zimejengwa from scratch, kuna sehemu karibu 10km wali modify reli ya zamani ndo wakaungansha na reli mpya.... Kwahivyo ku compare heavy rail ya Kenya ambayo inabeba tani zaidi ya 22Million kwa mwaka na light rail ndogo ya Senegal amabyo pesa nyingi imeenda kununua vichwa na ni reli ya abiria pekee ni upuzi
NI sawa na ku compare light rail ya Ethioia na SGR ya Kenya
![]()
![]()
Mbona hao wa Ethiopia wenyewe hawakueka SGR yao iwe kama hii light rail yao?
----------
Alafu kuhusu SGR ya Ethiopia, yao inabeba 10Million tonnes pekee, ukilinganisha na ya Kenya ya 22Million, hapo tayari inatosha kumaliza hio comparizon, tena sehemu kubwa imejengewa chini chini kama hio yenu, kwahivyo kukiwa na mafuriko reli inafunikwa na maji, mbali na hapo kuna changamoto tele hata ukifika kwa forum yao kule SSC mara kwa mara unakuta wanasema hata afadhali wangejenga reli kama ya Kenya !
Siku zote hesabu za cost ya reli zinahesabiwa kutumia route length na wala sio length of track........ manake kama ni kutumia track length basi itabidi uongeze 137km kwa hesabu za rei ya Kenya hadi iwe 609km badala ya ile 472km ambayo hutumika kupata hesabu ya cost per km.Nadhani hiyo reli ya Senegal ni double track kwa hiyo length yake itakuwa km 110.
Isaka-Dodoma