Phase two of SGR to take 36 months

Phase two of SGR to take 36 months

Jay456watt

JF-Expert Member
Joined
Aug 23, 2016
Posts
10,356
Reaction score
7,992
sgrpic.jpg

The completion time for the second phase of the Standard Gauge Railway from Nairobi to Naivasha has been reduced to 36 months from the initial 54 months.

Transport Cabinet Secretary James Macharia said construction of SGR Phase 2A will resume after the National Environment Tribunal rules on a dispute challenging the project.

The tribunal temporarily stopped the construction after activist Okiyah Omtatah and lobby group Kenya Coalition for Wildlife Conservation and Management filed an appeal against Kenya Railways and China Road and Bridges Corporation.

The applicants sought orders stopping construction until the environmental and social impact assessments of the project are carried out.

They said the project was commenced by tunnelling in Ngong Hills and approval of the route through Nairobi National Park and densely populated areas in Kajiado County without following the law.

But CS Macharia on Friday exuded confidence that the tribunal will issue a favourable ruling and allow the project to proceed.

“We have acquired land and upon disposal of that case the process will be fast tracked thereafter,” Mr Macharia said.
 
200km siyo mwisho wa mradi, ni hatua ya kwanza tu. Pia itakuwa ni bora zaid kuliko yenu hiyo ya gari moshi
please refer to Kenya's SGR stations and compare them with urs...haha yaani kama masoko ya kariakor...kwa treni bila shaka mtakua na treni zenye sura nzuri kuliko hizi ila project sio urembo...project ni economic impact...and from what we have seen in the last few months, the economic impact has been tremendous...finally, trains can be replaced with time but stations cannot..we already have plans to make it electric in 4 years time when we have enough power...Lamu Coal Plant will be complete by 2020 and will add 1050 MW of power to Kenya's grid...Olkaria Power plant and Lake Turkana wind power are already complete and will add 500 MW of electricity altogether...so it wont be long before we buy those electric trains...mtashtuka tukinunua wakati bado mko mnajanega reli yenu sababu mwendo wenu wa ujenzi ni wa konokono....
 
sgrpic.jpg

The completion time for the second phase of the Standard Gauge Railway from Nairobi to Naivasha has been reduced to 36 months from the initial 54 months.

Transport Cabinet Secretary James Macharia said construction of SGR Phase 2A will resume after the National Environment Tribunal rules on a dispute challenging the project.

The tribunal temporarily stopped the construction after activist Okiyah Omtatah and lobby group Kenya Coalition for Wildlife Conservation and Management filed an appeal against Kenya Railways and China Road and Bridges Corporation.

The applicants sought orders stopping construction until the environmental and social impact assessments of the project are carried out.

They said the project was commenced by tunnelling in Ngong Hills and approval of the route through Nairobi National Park and densely populated areas in Kajiado County without following the law.

But CS Macharia on Friday exuded confidence that the tribunal will issue a favourable ruling and allow the project to proceed.

“We have acquired land and upon disposal of that case the process will be fast tracked thereafter,” Mr Macharia said.


Sasa hiyo 2 phase itapita Kenyan Central Republic au Peoples Republic of Kenya?
 
please refer to Kenya's SGR stations and compare them with urs...haha yaani kama masoko ya kariakor...kwa treni bila shaka mtakua na treni zenye sura nzuri kuliko hizi ila project sio urembo...project ni economic impact...and from what we have seen in the last few months, the economic impact has been tremendous...finally, trains can be replaced with time but stations cannot..we already have plans to make it electric in 4 years time when we have enough power...Lamu Coal Plant will be complete by 2020 and will add 1050 MW of power to Kenya's grid...Olkaria Power plant and Lake Turkana wind power are already complete and will add 500 MW of electricity altogether...so it wont be long before we buy those electric trains...mtashtuka tukinunua wakati bado mko mnajanega reli yenu sababu mwendo wenu wa ujenzi ni wa konokono....
Yakwenu imejengwa kwa mda gani?
Pia hujue kuwa hii ni selikari ya kazi tu, hatuma mda kwa kulemba. Mkandalasi akiambiwa mf atumie mda wa miezi 12 yeye inabidi amalize kwa miezi 10
 
Yakwenu imejengwa kwa mda gani?
Pia hujue kuwa hii ni selikari ya kazi tu, hatuma mda kwa kulemba. Mkandalasi akiambiwa mf atumie mda wa miezi 12 yeye inabidi amalize kwa miezi 10
yetu imechukua 2 years construction and 6 months of testing for the first phase...second phase 3 years...so in total it will be 5 years...not bad
 