BUSINESS
POSTED 2 DAYS AGO
Rusumo project to ease power costs
By Khalifa Said @RealKhalifax ksaid@tz.nationmedia.com
IN SUMMARY
Speaking during the launch of the construction of the 80MW Hydroelectric Project yesterday, Ms Bella Bird, the World Bank Country Director for Tanzania, Burundi, Malawi and Somalia said the expected cost of power generated by the project plant was 6c per Kwh,which is much lower than the average cost of power in Burundi (10c/Kwh), Rwanda (26c/Kwh) and Tanzania (12c/Kwh).
Dar es Salaam. The Rusumo Falls Hydroelectric Project is expected to reduce power generation costs in all beneficiary countries of Tanzania, Burundi and Rwanda.
Speaking during the launch of the construction of the 80MW Hydroelectric Project yesterday, Ms Bella Bird, the World Bank Country Director for Tanzania, Burundi, Malawi and Somalia said the expected cost of power generated by the project plant was 6c per Kwh,which is much lower than the average cost of power in Burundi (10c/Kwh), Rwanda (26c/Kwh) and Tanzania (12c/Kwh).
Ms Bird added that offering the opportunity to shift from higher cost thermal generation, the hydroelectric plant would also place participating countries in sustainable development.
Ms Bird said there was no question that access to energy drove development and that people in towns and villages across the region were hungry for affordable and reliable power in their homes.
“Power creates jobs and opportunities. It helps to create hope for the future and stability. We know from across the world that it is not only access, but also affordability that matters, especially to poor households,” said the WB regional director. The ceremony, which took place at the Rusumo site on the Kagera River, was witnessed by ministers of Energy, Water and Finance from all the three beneficiary countries, board members of Rusumo Power Company Limited from respective shareholder countries, representatives of the World Bank and the African Development Bank (AfDB), the financiers of the project and other key stakeholders.
The construction of the power generation plant is financed by the World Bank at $340 million, while transmission lines that will connect the power plant to the national grids in the three countries is financed by the AfDB at $121 million. The project will provide an additional 26.6MW to each of the beneficiary member states and strengthen power interconnection.
SHARE THIS STORY
http://mobile.thecitizen.co.tz/busi...04484-3872084-format-xhtml-n2mk82z/index.html
Pitia hapa pia kupunguza wivu
Energy
March 30, 2017
Burundi, Rwanda And Tanzania Commence 80 MW Hydroelectric Construction
Posted By: newbusin
Burundi, Rwanda and Tanzania today witnessed ground-breaking ceremony for construction of the 80 MW Regional Rusumo Falls Hydro-electric Project.
The Rusumo falls is located on the Kagera River on the border between Rwanda (Southeast) and Tanzania (Northwest) and about 25 kilometers downstream of Burundi, Rwanda and Tanzania common border point. The Falls are approximately 15 meters high and 40 meters wide. The catchment at the falls drains to the territories of Tanzania & Rwanda.
The Rusumo falls was identified as a potential area for hydropower generation as early as 1970s, to address inadequate energy, which is one of the major socio-economic development challenges facing Burundi, Rwanda and Tanzania, which still have low rates of electricity access.
Although the three partner states discussed over several years to move Rusumo falls project forward, implementation of the highly needed project was not forthcoming due to a number of reasons, including lack of commitment from the partner states, lack of investment finance, civil conflict as well as absence of a joint institution to coordinate the project.
Construction of the Power Generation Plant is financed by
the World Bank at a cost of USD 340 million while the transmission lines that will connect the power plant to the national grids in the three countries is financed by
the African Development Bank (AfDB) at a cost of USD 121 million.
The ceremony, which took place at the Rusumo site on the Kagera River, is witnessed by Ministers of Energy, Water and Finance from the three beneficiary countries namely; Burundi, Rwanda and Tanzania. Board Members of Rusumo Power Company Limited from the respective shareholder countries, representatives of the World Bank and the African Development Bank, who are financiers of the project, as well as other key stakeholders, have also attended.
Among the numerous benefits, the project will provide an additional 26.6MW to each of the beneficiary Member States and strengthen the regional power interconnection between the countries. It will improve livelihoods of the 7,000 households in the beneficiary districts under the local area development program and another 188 households directly affected by the projects through livelihood restoration program. This is in addition to providing job opportunities for over 500 skilled, non- skilled and casual workers from the three beneficiary countries.
Construction of the Power Plant is expected to last three years, until 2020. CGCOC Group Ltd – Jiangxi Water & Hydropower Construction Company Ltd Joint Venture (CGCOC – JWHC JV) of P.R. China will execute the Civil Works/Supply and Installation of Hydro-Mechanical Equipment, while the Consortium Rusumo Falls Andritz Hydro GmbH (Germany) and Andritz Hydro PVT Ltd (India), will supply and install Electro-Mechanical Equipment for power plant.
The Rusumo Power Plant is being implemented by the Nile Equatorial Lakes Subsidiary Action Program Coordination Unit (NELSAP-CU) mandated by the three countries through the Special Purpose Vehicle, the Rusumo Power Company Ltd (RPCL). The RPCL is jointly owned utility company by the three countries, institutional mechanism set-up for the co-management of power generation and supply to national power utilities.
NELSAP Regional Coordinator, Eng. Elicad Elly Nyabeeya, recognises that the Regional Rusumo Falls Hydro-electric Project is complex, transboundary in nature, with a number of different components and several key stakeholders, thus demands effective coordination and management to deliver the required Power Plant, associated transmission lines, and sub-stations in a timely manner. He reiterates that once the project is completed, it will enhance socio-economic growth, reinforce regional cooperation, partnership and peace within the Kagera River Basin countries.
The development of the Regional Rusumo Hydroelectric Project idea was revived in 2006 and championed by Nile Equatorial Lakes Subsidiary Action Program Coordination Unit (NELSAP-CU), the investment arm of
the Nile Basin Initiative (NBI).
The Project design is a Run-of-River Development Scheme with a normal operating water level of 1,320 meters above mean sea level. The Run of River Development Scheme was selected by the beneficiary governments because it maintains the natural flow of the river and does not significantly modify the natural environment; it minimizes environmental and social impacts of the project and provides for the least cost implementation for environmental management and resettlemen.
Burundi, Rwanda and Tanzania commence 80 MW hydroelectric construction - new Business Ethiopia (nBE)