1970 report ilitumiwa kama refence tu,
Nakimalizia hii presentation mpya ambayo ni ndefu sana, unatakiwa uache kazi zako na uisome kwa kutulia. Nitaileta brief yake.
Economic, Technical and Financial Feasibility of the Stiegler’s Gorge Hydropower Project, Tanzania. Review and updated by ,
Elizabeth Kurt's PhD,
Robert Bernstein PhD
Helmut Carstein PhD.
Botões Westburg FC Inst E
Hydropower Sustainability Assessment Protocol
Introduction
According to Tanzania’s 2015 National Energy Policy, availability, affordability, reliability and
access to modern energy services are key ingredients towards socio-economic development.
Current power generation capacity is approximately 1,500 MW, which is very low for a country
with 59 million people. The largest single potential generation project in Tanzania is a
hydropower project at Stiegler’s Gorge on the Rufiji River, which would expand generation
capacity by 2,100 MW. In the latest update of the Power System Master Plan (PSMP) from 2016 - 2022.
In association with the Government of Tanzania and Ethiopian National Hydropower Generation Company, our team has done a thorough and effected review of the following:
Hydropower design
Dam design
Power generation design
Power transmission line design
Over all project implementation planning.
1)DESCRIPTIVE HYDROLOGY-TEAM
2)QUANTITATIVE HYDROLOGY-TEAM
3)HYDROGRAPH ANALYSIS-TEAM
a) the water energy resource sites
b) Evaluation to determine the feasibility of stiglers gorge hydro power dam
c) The criteria considered for site accessibility
d) Load or transmission proximity,
e) Land use,
f) Environmental sensitivities
g) Feasible potential project site
h) Estimates of the power potential
i) Development model not requiring a dam obstructing the watercourse
j) Formation of a reservoir.
k) Penstock running parallel to the stream
Hichi ni Kitabu cha kurasa 360. Cha review ya 2016 kabla ya kuanza ujenzi 2017.
Inawezekana wataalamu wa umeme kwao mwaka 1970, 1980 na 2016 ni miaka sawa? LABDATruncated